26.2.23

Finish 3rd Phase Works of Srinivasa Sethu on Fast Track - TTD Eo





TTD EO Sri AV Dharma Reddy urged officials concerned to coordinate with Railway officials and finish the pending works of Srinivasa Sethu like installing of six steel girders on a fast track by April 15.

 

Addressing a review meeting along with Tirupati Municipal Commissioner Smt Anupama Anjali at TTD Administrative Building on Saturday, TTD EO said 89% of works on Srinivas Sethu were completed and the remaining works to be cleared on a fast pace so as to commission the Sethu by May 15.

 

Among others, he instructed officials to speed up and complete the pavement works for pedestrians, greenery works at MS Subbulakshmi Circle, other painting works etc.

 

TTD JEO(H&E) Smt Sada Bhargavi, FA&CAO Sri Balaji, CE Sri Nageswara Rao, TMC SE Sri Mohan and others were also present.